I have three sets to ship by Fri & they have been notified. These three are all sponsors because I had to have a large amount for the next tubing order & meet the deadline for delivery. The supplier required it that way since Im the only one that they carry my product for.
I will have three sets for owed customers out by the end of next week using the tubes from that order I needed. Larry (he already knows) & two others that I haven't contacted yet. Not until the tubes arrive so that there wont be any problems.
These three sets that are to be out by Fri. have a few improvements not in the design but in the build process. It allows me to lose 2 to 2 1/2 hrs of build time on O-ports & about 45min to 1 hr on D-ports. All while making a better product & reducing the amount of finishing materials I use to make them look nice.
So I'm getting faster & more efficient while dealing with inventory to build them. Since I cant buy one tube at a time.
__________________
.
|