Quote:
Originally Posted by Ogre
Like it, like it, like it! I was wondering if you would be dried-in before the end of this week/coming weekend.
The major heavy rollup doors will take a while, but looks good so far.
Ogre
|
Thanks Ogre,
Been fighting the wind trying to finish this. Texas this time of year is very windy during the daytime as you know. We switched gears and got some nice LED headlamps and have been working at night when the wind dies down. We worked until 11PM on Friday night last. Neighbors were cool and did not call the cops. Should have it done in two weeks unless the rain does not stop.
Doors are going to be picked up this Saturday unless it is raining.
Not easy handling 17 ft sheets for the roof. lost two with a small gust and they went flying and were crumpled on the fence like pieces of paper.
The trim will take some time as they are one piece special ordered stuff. no seams. with the exception of the gutters. . No one makes a 50 ft seamless gutter for metal building.